Recently, Qinshan NPP is occupied with preparation for overhaul 115, sending 8 training engineers to conduct on-site training for overhaul contractors in Tongling, Anhui province. Tongling branch dispatches ...
The newly-built unit ignition blowing in power plant is an important milestone during the period from unit under construction to operation, indicating the new unit will shortly start up as a whole. According ...
根据土耳其ICDAS电厂调试指挥部的总体安排,定于5月15日进行冷态通风试验,皖能运检土耳其项目部通过认真细致的准备圆满完成#2锅炉冷态通风试验。 土耳其当地时间5月15日9点30分,业主、中钢、调试、安装单位、厂家代表及承担#...
5月13日下午至16日下午,秦山核电公司为115大修做准备,委派8名培训工程师来工程部实施大修承包商驻地培训,皖能运检铜陵分公司(工程部)积极配合做好培训工作。 这次培训主要为热工和电气专业,在相关分场的大力支持下,...
近日,临涣二期项目部圆满完成#3、4机组汽轮机快冷装置系统管道阀门安装和电缆铺设工作。 该快冷装置位于#3机汽机房零米层,需要安装压缩空气至快冷装置的进气管道和阀门,以及快冷装置至高、中压缸的供气管道和阀门。...
The main construction of unit #2 in ICDAS power plant in Turkey approaches its conclusion, and all commissioning work is going on. According to master schedule of unit #2 commissioning headquaters, main ...
2014年5月14日中午,由于华塑园区负荷的增加,#1发电机组负荷很快由240MW增长至280MW,随着负荷的增长,#11主变的油温和绕组温度迅速上升, 30分钟后#11主变绕组温度上升到82度,上层油温达到62度,热电厂运行车间三值电气副控黄海波立即汇报值长,...
土耳其ICDAS电厂#2机组的基建工作已近尾声,各项调试工作正在紧张的进行中,根据#2机组调试指挥部的总体计划5月10日进行主变倒送操作,刚到现场的土耳其项目部电气专业人员通过紧张、细致的准备,确保了#2主变倒送电操作一次成功。...
公司党委下发《关于开展“三严三实”集中学习教育及教育实践活动“回头看”工作的通知》后,运检铜陵分公司机关支部迅速布置落实,在全机关范围内,组织开展“三严三实”专题教育及教育实践活动“回头看”工作。 该支部将在近期组织中层管理人员开展集中学习教育活动。...
5月4日上午,运检铜陵分公司综合部召开部务会,学习公司文件。重申强调劳动纪律。 会上,通读学习了公司新近下发的《皖能铜陵发电有限公司脸部识别考勤系统管理规定》的通知。传达了公司人资部召开的考勤员会议精神,...